Schools | Calgary | Copperfield Elementary/Junior High School (Catholic)
Location:
855 Copperfield Blvd. SE
Community:
Start Date:
September 13th, 2010
Open:
September 2012
Project Updates
As of May 16th, 2012
- Construction completed
- School turned over to Calgary Board of Education
As of April 1st, 2012
- Final painting completed
- Commissioning verification completed
As of March 1st, 2012
- Acoustic wall treatment commenced
- Installation of washroom fixtures completed
- Fire alarm verification completed
As of January 31st, 2012
- Masonry at modular walls commenced
- Electrical and mechanical rough-ins commenced
As of December 31st, 2011
- Gymnasium equipment installation completed
- Locker installation completed
- Ceramic tiling on second floor completed
- Millwork installation commenced
As of November 30th, 2011
- Curbs, sidewalks and landscaping completed
- Elevator installation completed
As of October 31st, 2011
- Landscaping commenced
- Radiant panel installation commenced
- Prime and first coat of paint throughout building completed
As of September 30th, 2011
- Installation of concrete curbs commenced
- Site grading completed
- Hard surface play area completed
As of August 31st, 2011
- Masonry veneer completed
- Second floor painting commenced
- Light and car plug bases poured and associated electrical trenched
As of August 1st, 2011
- Fire spraying completed
- Second floor taping and sanding continues
- Interior gymnasium masonry completed
As of June 28th, 2011
- Fire spraying commenced
- Drywall installation on second floor completed
- Interior masonry on main floor commenced
As of June 1st, 2011
- Mechanical and eletrical rough-ins on second floor completed
- Drywall installation on second floor commenced
- Masonry on second floor completed
As of May 1st, 2011
- Ground thaw completed
- Boilers hoisted into place
- Window frames installation commenced
As of April 25th, 2011
- Delivery of second phase of high performance modular classrooms for a total of 16
As of March 31st, 2011
- Structural steel completed
- Roofing commenced
- Ground thaw commenced
As of February 28th, 2011
- Installation of steel stairs completed
- Construction of parapets commenced
As of January 24th, 2011
- Delivery of high performance modular classrooms
As of November 26th, 2010
- Erection of structural steel
As of November 19th, 2010
- Official sod turning and ground blessing ceremony celebrated on November 18, 2010
As of September 22nd, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school’s foundation
Showing 1 update(s) out of 20 | Show All