Schools | Calgary | Copperfield Elementary/Junior High School (Catholic)


School Board:
Grades:
K-9
# of Students:
396.5
Location:
855 Copperfield Blvd. SE
Community:
Start Date:
September 13th, 2010
Open:
September 2012

Project Updates

As of May 16th, 2012
  • Construction completed
  • School turned over to Calgary Board of Education
As of April 1st, 2012
  • Final painting completed
  • Commissioning verification completed
As of March 1st, 2012
  • Acoustic wall treatment commenced
  • Installation of washroom fixtures completed
  • Fire alarm verification completed
As of January 31st, 2012
  • Masonry at modular walls commenced
  • Electrical and mechanical rough-ins commenced
As of December 31st, 2011
  • Gymnasium equipment installation completed
  • Locker installation completed
  • Ceramic tiling on second floor completed
  • Millwork installation commenced
As of November 30th, 2011
  • Curbs, sidewalks and landscaping completed
  • Elevator installation completed
As of October 31st, 2011
  • Landscaping commenced
  • Radiant panel installation commenced
  • Prime and first coat of paint throughout building completed
As of September 30th, 2011
  • Installation of concrete curbs commenced
  • Site grading completed
  • Hard surface play area completed
As of August 31st, 2011
  • Masonry veneer completed
  • Second floor painting commenced
  • Light and car plug bases poured and associated electrical trenched
As of August 1st, 2011
  • Fire spraying completed
  • Second floor taping and sanding continues
  • Interior gymnasium masonry completed
As of June 28th, 2011
  • Fire spraying commenced
  • Drywall installation on second floor completed
  • Interior masonry on main floor commenced
As of June 1st, 2011
  • Mechanical and eletrical rough-ins on second floor completed
  • Drywall installation on second floor commenced
  • Masonry on second floor completed
As of May 1st, 2011
  • Ground thaw completed
  • Boilers hoisted into place
  • Window frames installation commenced
As of April 25th, 2011
  • Delivery of second phase of high performance modular classrooms for a total of 16
As of March 31st, 2011
  • Structural steel completed
  • Roofing commenced
  • Ground thaw commenced
As of February 28th, 2011
  • Installation of steel stairs completed
  • Construction of parapets commenced
As of January 24th, 2011
  • Delivery of high performance modular classrooms
As of November 26th, 2010
  • Erection of structural steel
As of November 19th, 2010
  • Official sod turning and ground blessing ceremony celebrated on November 18, 2010
As of September 22nd, 2010
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school’s foundation
Showing 1 update(s) out of 20 | Show All

What's New at B2L

May 8th, 2012

The ASAP II schools have been named by their respective school boards.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.