Schools | Calgary | Coventry Hills Middle School (Public)
Location:
12056 Coventry Hills Way NE
Community:
Start Date:
August 2nd, 2010
Open:
September 2012
Project Updates
As of May 1st, 2012
- Construction completed
- School has been turned over to Calgary Board of Education
As of March 1st, 2012
- Acoustic wall treatment completed
- Installation of mechanical fixtures completed
- Installation of washroom accessories completed
- Final architectural, electrical and mechanical inspections completed
As of January 31st, 2012
- Interior wood doors and hardware installed
- Elevator installation completed
- Installation of chain link fence commenced
As of December 31st, 2011
- Gymnasium equipment installation completed
- Installation of gymnasium hardwood flooring completed
- Millwork installation commenced
- Washroom toilets and sinks installed and partitions completed
As of November 30th, 2011
- Ceramic tiling of main floor washroom floors completed
- Locker installation completed
- Curbs and sidewalks completed
As of October 31st, 2011
- Prime coat of paint on main floor completed
- Installation of radiant panel in gymnasium and on second floor completed
- Landscaping completed
As of September 30th, 2011
- Drywall installation on main floor completed
- Curbs, sidewalks and paving completed
- Elevator installed
As of August 31st, 2011
- Washroom floors leveled for ceramic tile installation
- Site grading for landscaping completed
- Duct work in main gymnasium completed
As of August 1st, 2011
- Second floor primer painting continues
- Sprinkler installation on main floor progresses
- Retaining wall backfilled
As of June 28th, 2011
- Site grading commenced
- Fire proofing completed
- Drywall installation on second floor completed
As of June 1st, 2011
- Mechanical and electrical wall rough-ins on main floor continues
- Sprinkler installation on main floor continues
- Insulation to second floor wall partitions completed
As of May 1st, 2011
- Drywall installation on second floor commenced
- Roofing completed
- Window frames and glass installation completed
As of April 28th, 2011
- Delivery of second phase of high performance classrooms for a total of 16
As of March 31st, 2011
- Mechanical and electrical rough-ins commenced
- West side retaining wall completed
- Sprinkler installation commenced
As of February 28th, 2011
- Construction of masonry firewall completed
As of January 31st, 2011
- Structural steel completed
As of November 29th, 2010
- Erection of structural steel
As of October 12th, 2010
- Delivery of high performance modular classrooms
As of August 11th, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school’s foundation
As of June 29th, 2010
- Official ground breaking ceremony
Showing 1 update(s) out of 20 | Show All