Schools | Calgary | Coventry Hills Middle School (Public)


School Board:
Grades:
5-9
# of Students:
900
Location:
12056 Coventry Hills Way NE
Community:
Start Date:
August 2nd, 2010
Open:
September 2012

Project Updates

As of May 1st, 2012
  • Construction completed
  • School has been turned over to Calgary Board of Education
As of March 1st, 2012
  • Acoustic wall treatment completed
  • Installation of mechanical fixtures completed
  • Installation of washroom accessories completed
  • Final architectural, electrical and mechanical inspections completed
As of January 31st, 2012
  • Interior wood doors and hardware installed
  • Elevator installation completed
  • Installation of chain link fence commenced
As of December 31st, 2011
  • Gymnasium equipment installation completed
  • Installation of gymnasium hardwood flooring completed
  • Millwork installation commenced
  • Washroom toilets and sinks installed and partitions completed
As of November 30th, 2011
  • Ceramic tiling of main floor washroom floors completed
  • Locker installation completed
  • Curbs and sidewalks completed
As of October 31st, 2011
  • Prime coat of paint on main floor completed
  • Installation of radiant panel in gymnasium and on second floor completed
  • Landscaping completed
As of September 30th, 2011
  • Drywall installation on main floor completed
  • Curbs, sidewalks and paving completed
  • Elevator installed
As of August 31st, 2011
  • Washroom floors leveled for ceramic tile installation
  • Site grading for landscaping completed
  • Duct work in main gymnasium completed
As of August 1st, 2011
  • Second floor primer painting continues
  • Sprinkler installation on main floor progresses
  • Retaining wall backfilled
As of June 28th, 2011
  • Site grading commenced
  • Fire proofing completed
  • Drywall installation on second floor completed
As of June 1st, 2011
  • Mechanical and electrical wall rough-ins on main floor continues
  • Sprinkler installation on main floor continues
  • Insulation to second floor wall partitions completed
As of May 1st, 2011
  • Drywall installation on second floor commenced
  • Roofing completed
  • Window frames and glass installation completed
As of April 28th, 2011
  • Delivery of second phase of high performance classrooms for a total of 16
As of March 31st, 2011
  • Mechanical and electrical rough-ins commenced
  • West side retaining wall completed
  • Sprinkler installation commenced
As of February 28th, 2011
  • Construction of masonry firewall completed
As of January 31st, 2011
  • Structural steel completed
As of November 29th, 2010
  • Erection of structural steel
As of October 12th, 2010
  • Delivery of high performance modular classrooms
As of August 11th, 2010
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school’s foundation
As of June 29th, 2010
  • Official ground breaking ceremony
Showing 1 update(s) out of 20 | Show All

What's New at B2L

May 8th, 2012

The ASAP II schools have been named by their respective school boards.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.