Schools | Edmonton | Ellerslie Elementary/Junior High School (Public)
Location:
4110 Savaryn Drive SW
Community:
Start Date:
August 30th, 2010
Open:
September 2012
Project Updates
As of May 10th, 2012
- Construction completed
- School turned over to Edmonton Public Schools
As of April 1st, 2012
- Commissioning of mechanical and electrical systems completed
As of March 1st, 2012
- Washroom accessories installed
- Installation of mechanical fixtures completed
- Fire alarm system verification completed
As of January 31st, 2012
- Gymnasium hardwood flooring completed including line painting
- Bike racks installed
- Installation of wood doors and hardware completed
- Installation of mechanical fixtures commenced
As of December 31st, 2011
- Millwork installation completed
- Installation of vinyl tile, carpet and ceramic tile continues on main floor
- Installation of lockers completed
- Installation of electrical fixtures on main floor commenced
As of November 30th, 2011
- Installation of gymnasium equipment completed
- Elevator installation completed
- Landscaping completed
As of October 31st, 2011
- Asphalt paving to parking lot completed
- Ceramic tiling of second floor washrooms completed
- Landscaping progresses
As of September 30th, 2011
- Prime and first coat of paint on second floor completed
- Sidewalks and curbs completed
- Installation of light fixtures and radiant panels progresses
As of August 31st, 2011
- Insulation of piping on second floor completed
- Construction of site sidewalks and curbs commenced
- Mechanical and electrical rough-ins progresses
As of August 1st, 2011
- Fireproofing on main floor commenced
- Installation of second floor drywall continues
- Mechanical and electrical rough-ins on second floor completed
As of June 28th, 2011
- Mechanical work below main floor slab completed
- Installation of window frames continues
As of June 1st, 2011
- Exterior masonry continues
- Parapet construction completed
- Drywall installation on second floor commenced
As of May 1st, 2011
- Second floor concrete slab completed
- Window frames installation commenced
As of April 5th, 2011
- Delivery of second phase of high performance modular classrooms for a total of 14
As of March 31st, 2011
- Structural steel completed
- East masonry firewall completed
- Mechanical and electrical rough-ins to the second floor deck completed
As of February 28th, 2011
- Construction of masonry firewall commenced
As of November 26th, 2010
- Delivery of first phase of high performance modular classrooms
As of November 9th, 2010
- Erection of structural steel
As of September 8th, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school's foundation
Showing 1 update(s) out of 19 | Show All
