Schools | Edmonton | Ellerslie Elementary/Junior High School (Public)


School Board:
Grades:
K-9
# of Students:
850
Location:
4110 Savaryn Drive SW
Community:
Start Date:
August 30th, 2010
Open:
September 2012

Project Updates

As of May 10th, 2012
  • Construction completed
  • School turned over to Edmonton Public Schools
As of April 1st, 2012
  • Commissioning of mechanical and electrical systems completed
As of March 1st, 2012
  • Washroom accessories installed
  • Installation of mechanical fixtures completed
  • Fire alarm system verification completed
As of January 31st, 2012
  • Gymnasium hardwood flooring completed including line painting
  • Bike racks installed
  • Installation of wood doors and hardware completed
  • Installation of mechanical fixtures commenced
As of December 31st, 2011
  • Millwork installation completed
  • Installation of vinyl tile, carpet and ceramic tile continues on main floor
  • Installation of lockers completed
  • Installation of electrical fixtures on main floor commenced
As of November 30th, 2011
  • Installation of gymnasium equipment completed
  • Elevator installation completed
  • Landscaping completed
As of October 31st, 2011
  • Asphalt paving to parking lot completed
  • Ceramic tiling of second floor washrooms completed
  • Landscaping progresses
As of September 30th, 2011
  • Prime and first coat of paint on second floor completed
  • Sidewalks and curbs completed
  • Installation of light fixtures and radiant panels progresses
As of August 31st, 2011
  • Insulation of piping on second floor completed
  • Construction of site sidewalks and curbs commenced
  • Mechanical and electrical rough-ins progresses
As of August 1st, 2011
  • Fireproofing on main floor commenced
  • Installation of second floor drywall continues
  • Mechanical and electrical rough-ins on second floor completed
As of June 28th, 2011
  • Mechanical work below main floor slab completed
  • Installation of window frames continues
As of June 1st, 2011
  • Exterior masonry continues
  • Parapet construction completed
  • Drywall installation on second floor commenced
As of May 1st, 2011
  • Second floor concrete slab completed
  • Window frames installation commenced
As of April 5th, 2011
  • Delivery of second phase of high performance modular classrooms for a total of 14
As of March 31st, 2011
  • Structural steel completed
  • East masonry firewall completed
  • Mechanical and electrical rough-ins to the second floor deck completed
As of February 28th, 2011
  • Construction of masonry firewall commenced
As of November 26th, 2010
  • Delivery of first phase of high performance modular classrooms
As of November 9th, 2010
  • Erection of structural steel
As of September 8th, 2010
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school's foundation
Showing 1 update(s) out of 19 | Show All

What's New at B2L

May 8th, 2012

The ASAP II schools have been named by their respective school boards.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.