Schools | Edmonton | Griesbach Elementary/Junior High School (Public)
Location:
304 Griesbach School Road NW
Community:
Start Date:
October 15th, 2010
Open:
September 2012
Project Updates
As of May 10th, 2012
- Construction completed
- School turned over to Edmonton Public Schools
As of April 1st, 2012
- Air flush of building commenced
As of March 1st, 2012
- Final coat of paint and paint touch ups completed
- Final cleaning, sealing and waxing of floors completed
- Commissioning completed
As of January 31st, 2012
- Installation of sliding shutter and sliding glass doors completed
- Installation of fabric covered acoustic panels completed
- Installation of wood doors and hardware completed
- Installation of gymnasium hardwood flooring completed
As of December 31st, 2011
- Installation of millwork and countertops completed
- Ceramic tile installation completed
- Installation of gymnasium equipment completed
- Installation of gymnasium hardwood flooring commenced
As of November 30th, 2011
- Installation of wood doors to second floor completed
- Classroom ceiling tiles installed
- Mechanical, electrical and controls commissioning commenced
As of October 31st, 2011
- Drywall installation completed
- Interior painting commenced
- Modular classroom tie-ins completed
As of September 30th, 2011
- Painting of exterior doors and gymnasium commenced
- Asphalt paving completed
- Landscaping completed
As of August 31st, 2011
- Interior masonry completed
- Sidewalk installation progresses
- Drywall installation progresses
As of August 1st, 2011
- Installation of exterior window frames completed
- Mechanical and electrical rough-ins progresses
- Electrical rough-in for parking lot completed
As of June 28th, 2011
- Masonry veneer completed
- Mechanical and electrical rough-ins commenced
- Site grading continues for preparation of site sidewalks
As of June 1st, 2011
- Parapet installation completed
- Installation of exterior windows commenced
- Site grading commenced
As of May 1st, 2011
- Mechanical and electrical rough-ins commenced
- Parapet installation progresses
- Masonry block work continues
As of March 31st, 2011
- Water and sanitary lines connected
- Exterior steel studs commenced
As of March 18th, 2011
- Delivery of 14 high performance modular classrooms
As of January 31st, 2011
- Erection of structural steel
- Construction of exterior masonry firewall completed
As of October 27th, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school’s foundation
Showing 1 update(s) out of 17 | Show All