Schools | Edmonton | Griesbach Elementary/Junior High School (Public)


School Board:
Grades:
K-9
# of Students:
600
Location:
304 Griesbach School Road NW
Community:
Start Date:
October 15th, 2010
Open:
September 2012

Project Updates

As of May 10th, 2012
  • Construction completed
  • School turned over to Edmonton Public Schools
As of April 1st, 2012
  • Air flush of building commenced
As of March 1st, 2012
  • Final coat of paint and paint touch ups completed
  • Final cleaning, sealing and waxing of floors completed
  • Commissioning completed
As of January 31st, 2012
  • Installation of sliding shutter and sliding glass doors completed
  • Installation of fabric covered acoustic panels completed
  • Installation of wood doors and hardware completed
  • Installation of gymnasium hardwood flooring completed
As of December 31st, 2011
  • Installation of millwork and countertops completed
  • Ceramic tile installation completed
  • Installation of gymnasium equipment completed
  • Installation of gymnasium hardwood flooring commenced
As of November 30th, 2011
  • Installation of wood doors to second floor completed
  • Classroom ceiling tiles installed
  • Mechanical, electrical and controls commissioning commenced
As of October 31st, 2011
  • Drywall installation completed
  • Interior painting commenced
  • Modular classroom tie-ins completed
As of September 30th, 2011
  • Painting of exterior doors and gymnasium commenced
  • Asphalt paving completed
  • Landscaping completed
As of August 31st, 2011
  • Interior masonry completed
  • Sidewalk installation progresses
  • Drywall installation progresses
As of August 1st, 2011
  • Installation of exterior window frames completed
  • Mechanical and electrical rough-ins progresses
  • Electrical rough-in for parking lot completed
As of June 28th, 2011
  • Masonry veneer completed
  • Mechanical and electrical rough-ins commenced
  • Site grading continues for preparation of site sidewalks
As of June 1st, 2011
  • Parapet installation completed
  • Installation of exterior windows commenced
  • Site grading commenced
As of May 1st, 2011
  • Mechanical and electrical rough-ins commenced
  • Parapet installation progresses
  • Masonry block work continues
As of March 31st, 2011
  • Water and sanitary lines connected
  • Exterior steel studs commenced
As of March 18th, 2011
  • Delivery of 14 high performance modular classrooms
As of January 31st, 2011
  • Erection of structural steel
  • Construction of exterior masonry firewall completed
As of October 27th, 2010
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school’s foundation
Showing 1 update(s) out of 17 | Show All

What's New at B2L

May 8th, 2012

The ASAP II schools have been named by their respective school boards.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.