Project Updates

As of May 15th, 2012
  • Construction completed
  • School turned over to Calgary Board of Education
As of March 1st, 2012
  • Commissioning to building completed
  • HVAC controls system completed
  • Installation of acoustic panels completed
As of January 31st, 2012
  • Elevator installation completed
  • Security installation completed
  • Electrical fixtures completed
As of December 31st, 2011
  • Main and second floor painting continues
  • Second floor millwork installation completed
  • Washroom partitions installation completed
As of November 30th, 2011
  • Sidewalks to site completed
  • Millwork installation continues
  • Installation of electrical lights continues
As of October 31st, 2011
  • Landscaping completed
  • Painting on main and second floors continues
  • Installation of exterior siding completed
As of September 30th, 2011
  • Sidewalk installation completed
  • Asphalt paving to main parking completed
  • Mechanical rooms completed
As of August 31st, 2011
  • Exterior masonry completed
  • Exterior window frame installation completed
  • Painting on second floor and in gymnasiums commenced
As of August 1st, 2011
  • Mechanical rough-in continues
  • Soil screening for landscaping completed
  • Sidewalk installation commenced
As of June 28th, 2011
  • Modular connection to building completed
  • Exterior window frame installation completed
  • Soil screening for landscaping commenced
As of June 1st, 2011
  • Exterior masonry commenced
  • Window and window frame installation continues
  • Drywall installation on second floor commenced
As of May 1st, 2011
  • Parapet framing completed
  • Masonry completed to washrooms on second floor
As of April 12th, 2011
  • Delivery of four high performance modular classrooms for a total of 16
As of March 31st, 2011
  • Roofing commenced
  • Window frame installation commenced
As of February 28th, 2011
  • Structural steel completed
As of January 31st, 2011
  • Construction of masonry firewall commenced
As of January 20th, 2011
  • Delivery of high performance modular classrooms
As of November 15th, 2010
  • Erection of structural steel
As of September 22nd, 2010
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school’s foundation
As of June 29th, 2010
  • Official ground breaking ceremony
Showing 1 update(s) out of 20 | Show All

What's New at B2L

May 8th, 2012

The ASAP II schools have been named by their respective school boards.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.