Schools | Calgary | Panorama Hills Middle School (Public)
Location:
405 Panatella Blvd. NW
Community:
Start Date:
September 13th, 2010
Open:
September 2012
Project Updates
As of May 15th, 2012
- Construction completed
- School turned over to Calgary Board of Education
As of March 1st, 2012
- Commissioning to building completed
- HVAC controls system completed
- Installation of acoustic panels completed
As of January 31st, 2012
- Elevator installation completed
- Security installation completed
- Electrical fixtures completed
As of December 31st, 2011
- Main and second floor painting continues
- Second floor millwork installation completed
- Washroom partitions installation completed
As of November 30th, 2011
- Sidewalks to site completed
- Millwork installation continues
- Installation of electrical lights continues
As of October 31st, 2011
- Landscaping completed
- Painting on main and second floors continues
- Installation of exterior siding completed
As of September 30th, 2011
- Sidewalk installation completed
- Asphalt paving to main parking completed
- Mechanical rooms completed
As of August 31st, 2011
- Exterior masonry completed
- Exterior window frame installation completed
- Painting on second floor and in gymnasiums commenced
As of August 1st, 2011
- Mechanical rough-in continues
- Soil screening for landscaping completed
- Sidewalk installation commenced
As of June 28th, 2011
- Modular connection to building completed
- Exterior window frame installation completed
- Soil screening for landscaping commenced
As of June 1st, 2011
- Exterior masonry commenced
- Window and window frame installation continues
- Drywall installation on second floor commenced
As of May 1st, 2011
- Parapet framing completed
- Masonry completed to washrooms on second floor
As of April 12th, 2011
- Delivery of four high performance modular classrooms for a total of 16
As of March 31st, 2011
- Roofing commenced
- Window frame installation commenced
As of February 28th, 2011
- Structural steel completed
As of January 31st, 2011
- Construction of masonry firewall commenced
As of January 20th, 2011
- Delivery of high performance modular classrooms
As of November 15th, 2010
- Erection of structural steel
As of September 22nd, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school’s foundation
As of June 29th, 2010
- Official ground breaking ceremony
Showing 1 update(s) out of 20 | Show All
