Schools | Langdon | Sarah Thompson Elementary School (Public)


School Board:
Grades:
K-5
# of Students:
450
Location:
42 – 4 Street NE
Community:
Start Date:
December 23rd, 2010
Open:
September 2012

Project Updates

As of May 16th, 2012
  • Construction completed
  • School turned over to Rocky View Schools
As of April 1st, 2012
  • Installation of acoustic panels completed
  • Installation of rubber flooring completed
  • Final painting completed
  • Mechanical and electrical finishes installed
As of March 1st, 2012
  • Installation of plumbing fixtures near completion
  • Installation of rubber flooring commenced
  • Final painting commenced
As of January 31st, 2012
  • Installation of gymnasium equipment completed
  • Light fixtures installed and operational
  • Door hardware installation commenced
As of December 31st, 2011
  • Ceramic tiling commenced
  • Priming and first coat painting completed
  • Boiler and mechanical rooms completed
As of November 30th, 2011
  • Landscaping completed
  • Drywall installation completed
  • Siding installation continues
As of October 31st, 2011
  • Curbs, sidewalks and paving completed
  • Masonry veneer completed
  • Mechanical and electrical rough-ins ongoing
As of September 30th, 2011
  • Curbs, sidewalks and paving commenced
  • Landscaping commenced
  • Interior painting commenced
As of August 31st, 2011
  • Interior door frames installed
  • Mechanical and electrical rough-ins progresses
  • Fireproofing completed
As of August 1st, 2011
  • Exterior gymnasium block walls completed
  • Parapets completed
As of June 28th, 2011
  • Masonry veneer completed
  • Window installation commenced
As of June 1st, 2011
  • Metal deck and parapet framing completed
  • Underground mechanical commenced
  • Building has been backfilled
As of May 1st, 2011
  • Metal deck commenced
  • Parapet framing commenced
As of April 14th, 2011
  • Delivery of 12 high performance modular classrooms
As of March 31st, 2011
  • Structural steel completed
  • Mechanical and electrical rough-ins commenced
As of February 28th, 2011
  • Erection of structural steel
As of January 12th, 2011
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school’s foundation
As of December 7th, 2010
  • Official ground breaking ceremony celebrated on December 3, 2010
Showing 1 update(s) out of 18 | Show All

What's New at B2L

May 8th, 2012

The ASAP II schools have been named by their respective school boards.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.