Schools | Langdon | Sarah Thompson Elementary School (Public)
Location:
42 – 4 Street NE
Community:
Start Date:
December 23rd, 2010
Open:
September 2012
Project Updates
As of May 16th, 2012
- Construction completed
- School turned over to Rocky View Schools
As of April 1st, 2012
- Installation of acoustic panels completed
- Installation of rubber flooring completed
- Final painting completed
- Mechanical and electrical finishes installed
As of March 1st, 2012
- Installation of plumbing fixtures near completion
- Installation of rubber flooring commenced
- Final painting commenced
As of January 31st, 2012
- Installation of gymnasium equipment completed
- Light fixtures installed and operational
- Door hardware installation commenced
As of December 31st, 2011
- Ceramic tiling commenced
- Priming and first coat painting completed
- Boiler and mechanical rooms completed
As of November 30th, 2011
- Landscaping completed
- Drywall installation completed
- Siding installation continues
As of October 31st, 2011
- Curbs, sidewalks and paving completed
- Masonry veneer completed
- Mechanical and electrical rough-ins ongoing
As of September 30th, 2011
- Curbs, sidewalks and paving commenced
- Landscaping commenced
- Interior painting commenced
As of August 31st, 2011
- Interior door frames installed
- Mechanical and electrical rough-ins progresses
- Fireproofing completed
As of August 1st, 2011
- Exterior gymnasium block walls completed
- Parapets completed
As of June 28th, 2011
- Masonry veneer completed
- Window installation commenced
As of June 1st, 2011
- Metal deck and parapet framing completed
- Underground mechanical commenced
- Building has been backfilled
As of May 1st, 2011
- Metal deck commenced
- Parapet framing commenced
As of April 14th, 2011
- Delivery of 12 high performance modular classrooms
As of March 31st, 2011
- Structural steel completed
- Mechanical and electrical rough-ins commenced
As of February 28th, 2011
- Erection of structural steel
As of January 12th, 2011
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school’s foundation
As of December 7th, 2010
- Official ground breaking ceremony celebrated on December 3, 2010
Showing 1 update(s) out of 18 | Show All
