Schools | Calgary | Taradale Middle School (Public)
Location:
750 Taradale Drive NE
Community:
Start Date:
August 30th, 2010
Open:
September 2012
Project Updates
As of May 1st, 2012
- Construction completed
- School turned over to Calgary Board of Education
As of April 1st, 2012
- Air flush of building commenced
As of March 1st, 2012
- Metal and wood doors hung and view glass installed
- Final painting on main and second floors completed
- Plumbing fixtures installed
- Gymnasium hardwood floor installed
As of January 31st, 2012
- Installation of gymnasium hardwood floor commenced
- Final painting on second floor commenced
- Pre-commissioning of mechanical and electrical equipment near completion
As of December 31st, 2011
- Gymnasium equipment installed
- Locker installation completed
- Electrical fixtures installed
- Installation of plumbing fixtures progresses
As of November 30th, 2011
- Prime and first coat painting on main floor completed
- Paving, sidewalks and landscaping completed
- Gymnasium painting completed
As of October 31st, 2011
- Elevator installed and ready for provincial inspection
- Radiant heat ceiling panel in second floor classroom completed
- Mechanical rough-ins and electrical wiring on main floor completed
As of September 30th, 2011
- Prime and first coat of paint on second floor near completion
- Concrete sidewalk, garbage and dust collector slabs completed
- Drywall installation on main floor completed
As of August 31st, 2011
- Primer painting on second floor progresses
- Drywall installation in gymnasiums completed
- Landscaping commenced
As of August 1st, 2011
- Light pole and car plug bases completed
- Site grading and top soil placement progresses
- Concrete curb for parking lot commenced
As of June 28th, 2011
- Drywall installation completed
- Fire spraying to second floor structural steel and deck progresses
- Site grading continues
As of June 1st, 2011
- Drywall installation on second floor progresses
- Masonry wall for gymnasium changing room completed
- Exterior masonry commenced
As of May 1st, 2011
- Second floor concrete topping completed
- Concrete floors poured for main and auxiliary gymnasiums
As of March 31st, 2011
- Gymnasium area has been thawed and recycled gravel installed to prepare for pouring the gymnasium's concrete flour
- Interior drywall and masonry commenced
- Mechanical and electrical rough-ins are progressing
- Window frame installation commenced
As of March 21st, 2011
- Delivery of second phase of high performance modular classrooms for a total of 16
As of February 28th, 2011
- Roofing installation commenced
- Exterior steel studs completed
As of January 31st, 2011
- Structural steel completed
- Construction of masonry firewall commenced
As of November 29th, 2010
- Erection of structural steel
As of November 4th, 2010
- Delivery of high performance modular classrooms
As of September 10th, 2010
- Official ground breaking ceremony held on September 9, 2010
As of September 8th, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school's foundation
Showing 1 update(s) out of 21 | Show All