Schools | Calgary | Taradale Middle School (Public)


School Board:
Grades:
5-9
# of Students:
674
Location:
750 Taradale Drive NE
Community:
Start Date:
August 30th, 2010
Open:
September 2012

Project Updates

As of May 1st, 2012
  • Construction completed
  • School turned over to Calgary Board of Education
As of April 1st, 2012
  • Air flush of building commenced
As of March 1st, 2012
  • Metal and wood doors hung and view glass installed
  • Final painting on main and second floors completed
  • Plumbing fixtures installed
  • Gymnasium hardwood floor installed
As of January 31st, 2012
  • Installation of gymnasium hardwood floor commenced
  • Final painting on second floor commenced
  • Pre-commissioning of mechanical and electrical equipment near completion
As of December 31st, 2011
  • Gymnasium equipment installed
  • Locker installation completed
  • Electrical fixtures installed
  • Installation of plumbing fixtures progresses
As of November 30th, 2011
  • Prime and first coat painting on main floor completed
  • Paving, sidewalks and landscaping completed
  • Gymnasium painting completed
As of October 31st, 2011
  • Elevator installed and ready for provincial inspection
  • Radiant heat ceiling panel in second floor classroom completed
  • Mechanical rough-ins and electrical wiring on main floor completed
As of September 30th, 2011
  • Prime and first coat of paint on second floor near completion
  • Concrete sidewalk, garbage and dust collector slabs completed
  • Drywall installation on main floor completed
As of August 31st, 2011
  • Primer painting on second floor progresses
  • Drywall installation in gymnasiums completed
  • Landscaping commenced
As of August 1st, 2011
  • Light pole and car plug bases completed
  • Site grading and top soil placement progresses
  • Concrete curb for parking lot commenced
As of June 28th, 2011
  • Drywall installation completed
  • Fire spraying to second floor structural steel and deck progresses
  • Site grading continues
As of June 1st, 2011
  • Drywall installation on second floor progresses
  • Masonry wall for gymnasium changing room completed
  • Exterior masonry commenced
As of May 1st, 2011
  • Second floor concrete topping completed
  • Concrete floors poured for main and auxiliary gymnasiums
As of March 31st, 2011
  • Gymnasium area has been thawed and recycled gravel installed to prepare for pouring the gymnasium's concrete flour
  • Interior drywall and masonry commenced
  • Mechanical and electrical rough-ins are progressing
  • Window frame installation commenced
As of March 21st, 2011
  • Delivery of second phase of high performance modular classrooms for a total of 16
As of February 28th, 2011
  • Roofing installation commenced
  • Exterior steel studs completed
As of January 31st, 2011
  • Structural steel completed
  • Construction of masonry firewall commenced
As of November 29th, 2010
  • Erection of structural steel
As of November 4th, 2010
  • Delivery of high performance modular classrooms
As of September 10th, 2010
  • Official ground breaking ceremony held on September 9, 2010
As of September 8th, 2010
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school's foundation
Showing 1 update(s) out of 21 | Show All

What's New at B2L

May 8th, 2012

The ASAP II schools have been named by their respective school boards.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.