Schools | Edmonton | The Hamptons Elementary/Junior High School (Public)


School Board:
Grades:
K-9
# of Students:
850
Location:
121 Hemingway Road
Community:
Start Date:
July 27th, 2010
Open:
September 2012

Project Updates

As of January 31st, 2012
  • Elevator inspection completed
  • Air and water balancing completed
  • Mechanical, electrical and controls commissioning completed
As of December 31st, 2011
  • Gymnasium hardwood flooring completed with game lines and finishing
  • Wood doors with hardware installation completed on main floor
  • Mechanical, electrical and controls commissioning commenced
  • Acoustical fabric panels to music rooms on second floor completed
As of November 30th, 2011
  • Elevator installation commenced
  • Exterior painting completed
  • Landscaping completed
As of October 31st, 2011
  • Elevator installation commenced
  • Exterior painting completed
  • Landscaping completed
As of October 1st, 2011
  • Installation of front entrance canopy and soffits commenced
  • Additional site sidewalks and asphalt completed
  • Landscaping progresses
As of August 31st, 2011
  • Locker installation on second floor completed
  • Asphalt overlay commenced
  • Drywall installation progresses
As of August 1st, 2011
  • Building energized with permanent power and electrical meter
  • Fireproofing to main floor completed
  • Commercial crossing completed and ready for asphalt overlay
As of June 28th, 2011
  • Drywall installation to second floor completed
  • Second floor painting commenced
  • Site grading progresses
As of June 1st, 2011
  • Exterior masonry commenced
  • Roofing completed
As of May 1st, 2011
  • Interior drywall installation commenced
  • Parapet framing completed
As of March 31st, 2011
  • Exterior window frame installation commenced
  • Roofing installation commenced
  • Mechanical and electrical rough-ins commenced
As of February 28th, 2011
  • Delivery of second phase of high performance modular classrooms for a total of 14
  • Roofing installation commenced
  • Water and sanitary line completed
As of January 31st, 2011
  • Structural steel completed
As of November 29th, 2010
  • Erection of structural steel
As of October 5th, 2010
  • Delivery of high performance modular classrooms
As of July 30th, 2010
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school’s foundation
Showing 1 update(s) out of 16 | Show All

What's New at B2L

January 30th, 2012

The ten ASAP II schools are taking shape and looking impressive.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.