Project Updates
As of January 31st, 2012
- Elevator inspection completed
- Air and water balancing completed
- Mechanical, electrical and controls commissioning completed
As of December 31st, 2011
- Gymnasium hardwood flooring completed with game lines and finishing
- Wood doors with hardware installation completed on main floor
- Mechanical, electrical and controls commissioning commenced
- Acoustical fabric panels to music rooms on second floor completed
As of November 30th, 2011
- Elevator installation commenced
- Exterior painting completed
- Landscaping completed
As of October 31st, 2011
- Elevator installation commenced
- Exterior painting completed
- Landscaping completed
As of October 1st, 2011
- Installation of front entrance canopy and soffits commenced
- Additional site sidewalks and asphalt completed
- Landscaping progresses
As of August 31st, 2011
- Locker installation on second floor completed
- Asphalt overlay commenced
- Drywall installation progresses
As of August 1st, 2011
- Building energized with permanent power and electrical meter
- Fireproofing to main floor completed
- Commercial crossing completed and ready for asphalt overlay
As of June 28th, 2011
- Drywall installation to second floor completed
- Second floor painting commenced
- Site grading progresses
As of June 1st, 2011
- Exterior masonry commenced
- Roofing completed
As of May 1st, 2011
- Interior drywall installation commenced
- Parapet framing completed
As of March 31st, 2011
- Exterior window frame installation commenced
- Roofing installation commenced
- Mechanical and electrical rough-ins commenced
As of February 28th, 2011
- Delivery of second phase of high performance modular classrooms for a total of 14
- Roofing installation commenced
- Water and sanitary line completed
As of January 31st, 2011
- Structural steel completed
As of November 29th, 2010
- Erection of structural steel
As of October 5th, 2010
- Delivery of high performance modular classrooms
As of July 30th, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school’s foundation
Showing 1 update(s) out of 16 | Show All