Schools | Calgary | Tuscany Middle School (Public)
Location:
150 Tuscany Way NW
Community:
Start Date:
July 27th, 2010
Open:
September 2012
Project Updates
As of May 15th, 2012
- Construction completed
- School turned over to Calgary Board of Education
As of March 1st, 2012
- Commissioning verification completed
As of January 31st, 2012
- Major mechanical equipment commissioned and running
- Auxiliary and main gymnasiums completed including equipment installation
As of December 31st, 2011
- Ceramic tiling completed
- Elevator installation completed
- Lockers installed
- Sprinkler installation on main and second floors completed
As of November 30th, 2011
- Auxiliary gymnasium hardwood floors installed
- Second floor painting completed
- Gymnasium equipment installed
As of October 31st, 2011
- Elevator installation completed
- Sprinkler installation on main and second floors completed
- Curbs, sidewalks and paving completed
As of September 30th, 2011
- Curbs, sidewalks and paving completed
- Landscaping completed
- Drywall installation on main floor completed
As of August 31st, 2011
- Elevator installation completed
- Sprinkler installation on both floors completed
- Second coat of painting on second floor completed
As of August 1st, 2011
- All interior masonry completed
- Exterior cladding and windows on front of school completed
- Exterior grading for landscaping completed
As of June 28th, 2011
- Second floor painting progresses
- Fire spraying completed
- Interior masonry completed
As of June 1st, 2011
- Drywall installation on second floor completed
- Electrical and mechanical rough-ins on second floor completed
- PVC roof membrane completed
As of May 1st, 2011
- Exterior sub-grade completed
- Window frames and glass installation completed
As of March 31st, 2011
- Electrical and mechanical rough-ins for second floor deck completed
- Electrical and mechanical services to high performance modular classrooms completed
- Ground thaw completed for entire main floor and gymnasium concrete floor has been poured
As of February 28th, 2011
- Roofing installation completed
- Second floor concrete completed
- Second floor masonry washrooms completed
- Window installation commenced
As of February 4th, 2011
- Delivery of second phase of high performance modular classrooms for a total of 16
As of January 31st, 2011
- Structural steel completed
- Construction of masonry firewalls completed
As of November 29th, 2010
- Erection of structural steel
As of October 12th, 2010
- Delivery of first phase of high performance modular classrooms
As of July 30th, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school’s foundation
As of June 25th, 2010
- Official ground breaking ceremony
Showing 1 update(s) out of 20 | Show All