Schools | Calgary | Tuscany Middle School (Public)


School Board:
Grades:
5-9
# of Students:
900
Location:
150 Tuscany Way NW
Community:
Start Date:
July 27th, 2010
Open:
September 2012

Project Updates

As of May 15th, 2012
  • Construction completed
  • School turned over to Calgary Board of Education
As of March 1st, 2012
  • Commissioning verification completed
As of January 31st, 2012
  • Major mechanical equipment commissioned and running
  • Auxiliary and main gymnasiums completed including equipment installation
As of December 31st, 2011
  • Ceramic tiling completed
  • Elevator installation completed
  • Lockers installed
  • Sprinkler installation on main and second floors completed
As of November 30th, 2011
  • Auxiliary gymnasium hardwood floors installed
  • Second floor painting completed
  • Gymnasium equipment installed
As of October 31st, 2011
  • Elevator installation completed
  • Sprinkler installation on main and second floors completed
  • Curbs, sidewalks and paving completed
As of September 30th, 2011
  • Curbs, sidewalks and paving completed
  • Landscaping completed
  • Drywall installation on main floor completed
As of August 31st, 2011
  • Elevator installation completed
  • Sprinkler installation on both floors completed
  • Second coat of painting on second floor completed
As of August 1st, 2011
  • All interior masonry completed
  • Exterior cladding and windows on front of school completed
  • Exterior grading for landscaping completed
As of June 28th, 2011
  • Second floor painting progresses
  • Fire spraying completed
  • Interior masonry completed
As of June 1st, 2011
  • Drywall installation on second floor completed
  • Electrical and mechanical rough-ins on second floor completed
  • PVC roof membrane completed
As of May 1st, 2011
  • Exterior sub-grade completed
  • Window frames and glass installation completed
As of March 31st, 2011
  • Electrical and mechanical rough-ins for second floor deck completed
  • Electrical and mechanical services to high performance modular classrooms completed
  • Ground thaw completed for entire main floor and gymnasium concrete floor has been poured
As of February 28th, 2011
  • Roofing installation completed
  • Second floor concrete completed
  • Second floor masonry washrooms completed
  • Window installation commenced
As of February 4th, 2011
  • Delivery of second phase of high performance modular classrooms for a total of 16
As of January 31st, 2011
  • Structural steel completed
  • Construction of masonry firewalls completed
As of November 29th, 2010
  • Erection of structural steel
As of October 12th, 2010
  • Delivery of first phase of high performance modular classrooms
As of July 30th, 2010
  • Arrival of work crews and heavy equipment
  • Site preparation for constructing the school’s foundation
As of June 25th, 2010
  • Official ground breaking ceremony
Showing 1 update(s) out of 20 | Show All

What's New at B2L

May 8th, 2012

The ASAP II schools have been named by their respective school boards.

For more information on Alberta Infrastructure and Alberta Education, please visit:

Alberta Infrastructure
Alberta Education

School Registration

How do I register my child for one of the new schools?

Please see Registration for contact information for the five school boards responsible for new school enrolment.

When will the new schools open?

The 10 new schools are scheduled to open in September 2012. Individual school boards will be able to provide specific enrolment information. Please go to Registration to contact them directly.