Schools | Okotoks | Westmount Elementary/Junior High School (Public)
Location:
240 Westland Street
Community:
Start Date:
August 16th, 2010
Open:
September 2012
Project Updates
As of May 1st, 2012
- Construction completed
- School turned over to Foothills School Division
As of April 1st, 2012
- Air flush of building commenced
As of March 1st, 2012
- Installation of acoustic panels completed
- Commissioning verification completed
- Architectural inspection completed
As of January 31st, 2012
- Door hardware installed
- Commissioning completed and awaiting verification
- Security and fire alarm system verified
As of December 31st, 2011
- Installation of gymnasium hardwood doors completed
- Installation of gymnasium equipment completed
- Final painting completed
As of November 30th, 2011
- Resilient flooring completed
- Installation of gymnasium equipment commenced
- Mechanical, electrical and controls commissioning commenced
As of October 31st, 2011
- Ceramic tiling of washroom walls completed
- Locker installation commenced
- Painting on main floor completed
As of September 30th, 2011
- Modular skirting and retaining walls completed
- Hard surface play area completed
- Prime and first coat of paint on main floor completed
As of August 31st, 2011
- Main floor drywall installation completed
- Ceramic tiling to second floor completed
- Parent drop-off sidewalk completed
As of August 1st, 2011
- Elevator installation commenced
- Interior masonry completed
- Site grading completed
As of June 28th, 2011
- Drywall installation on second floor completed
- Main floor masonry completed
- Fire spraying completed
As of June 1st, 2011
- Drywall installation on second floor commenced
- Mechanical and electrical rough-ins on main floor commenced
- Exterior masonry continues
As of May 1st, 2011
- Roofing completed
- Main floor masonry commenced
As of March 31st, 2011
- Exterior masonry completed
- Frost removal completed
- Window blocking completed
- Interior masonry commenced
As of March 23rd, 2011
- Delivery of second phase of high performance modular classrooms for a total of eight
As of February 28th, 2011
- Structural steel completed
- Construction of masonry firewalls completed
As of January 31st, 2011
- Construction of masonry firewall commenced
As of December 20th, 2010
- Erection of structural steel
As of December 10th, 2010
- Delivery of first phase of high performance modular classrooms
As of September 8th, 2010
- Arrival of work crews and heavy equipment
- Site preparation for constructing the school's foundation
As of September 1st, 2010
- Official sod-turning ceremony held on August 31, 2010
Showing 1 update(s) out of 21 | Show All